Implementation of this project will result in:
- Completion of the set of documents to enable tendering of works for the betterment/reconstruction/construction on the points of intervention on the SEETO route 2b, laid along the main road E762 (M18) from Sarajevo to Foča (Brod na Drini), to include, but not necessarily be limited to:
a) reviewed compliance of the conceptual design with the relevant legislation and spatial plans of the RS and FBiH,
b) optimised alignment laid down in the phase of the conceptual design, including introduction of connections to the adjacent roads and relocation of colliding road sections,
c) prepared preliminary design for betterment based on the conceptual design,
d) prepared extract of documents for obtaining of the spatial conditions and ultimately the spatial conformity for betterment interventions,
e) prepared feasibility study,
f) prepared environment impact assessment,
g) prepared road safety audit report,
h) prepared main design for the construction of betterment interventions, including interchanges, connections to the adjacent roads and relocation of colliding road sections,
i) revised main design by the consultant(s) authorized for revision under the Laws of RS and FBiH, respectively,
j) prepared tender dossier for construction of the respective betterment interventions, including interchanges, connections to the adjacent roads, and relocation of colliding road sections.